審計報告|屯赤連接路工程延誤、大幅更改 「超支」近 40 億
Audit report | Tuen Mun–Chek Lap Kok Link works delayed and substantially changed; “cost overruns” near $4 billion
屯門赤鱲角連接路工程在 2013 年獲批 467 億元撥款,用作前期和建造工程。今日(27日)發表的審計報告指出,工程涉及的八份合約中,有六份完工期延誤 3 至 27 個月,「超支」近 39.4 億元;若計及價格調整和扣除更改工程而上漲成本,額外支出更達 73.8 億元,佔原訂合約總額超過 22%。報告指,有關增幅未導致撥款 467 億工程超支。 報告又披露,屯赤隧道原沿車道設 45 個緊急通道艙口作疏散,屬首次用於香港隧道的新設計。但艙口井蓋事故頻生,曾三次「意外打開」構成安全風險,當局最終決定密封所有緊急通道艙口。
The Tuen Mun–Chek Lap Kok Link project was approved in 2013 for an allocation of $46.7 billion for preliminary and construction works. An audit report released today (27th) said that six of the project’s eight contracts were completed three to 27 months late, with “cost overruns” of nearly $3.94 billion. Taking into account price adjustments and increased costs arising from variation works, the additional expenditure reached $7.38 billion, representing more than 22% of the original total contract sum. The report said the increase did not result in the $46.7 billion project allocation being exceeded. The report also disclosed that 45 emergency access hatches had originally been installed along the carriageways of the Tuen Mun–Chek Lap Kok Link Tunnel for evacuation purposes. The design was the first of its kind to be used in a Hong Kong tunnel. However, incidents involving the hatch covers occurred frequently, and they accidentally opened three times, posing a safety risk. The authorities ultimately decided to seal all the emergency access hatches.